We set up end-to-end delivery governance. Function forums feed project forums, where the owner's team sits with the general contractor or EPCM. Those feed project steering and the board. Every level gets its own data, dashboards and decision rights, and every decision is logged.
Board approves gates, investment decisions and the budget envelope.
Project steering decides contingency drawdown and changes above threshold.
Project forums bring the owner's team and the GC or EPCM to one table for progress, change and interfaces.
The first weeks build the facts. The steering forums use them to decide.
Resolved within function authority, inside 2 working days.
Owner's team and contractor resolve within project authority.
Above threshold or critical: next session, or ad hoc within 48 hours.
Escalations follow the delegation of authority and come with options and a recommendation. Every decision is logged.
Portfolio and monthly project report: gate readiness, EAC against funding, critical path, contingency, top risks.
Integrated schedule, change log, interface and constraint registers, shared by owner and contractor.
Operational KPIs such as document status, productivity factor and look-ahead, each tied to a decision.