Project delivery governance

From function forums to the board, every decision on the record.

We set up end-to-end delivery governance. Function forums feed project forums, where the owner's team sits with the general contractor or EPCM. Those feed project steering and the board. Every level gets its own data, dashboards and decision rights, and every decision is logged.

Governance levels

Board
Project steering
Owner's teamproject forums
GC / EPCMproject forums
Contractorsinterfaces
Function forums

Board approves gates, investment decisions and the budget envelope.

Project steering decides contingency drawdown and changes above threshold.

Project forums bring the owner's team and the GC or EPCM to one table for progress, change and interfaces.

Monthly governance cycle

Week 1
Data cut-off
Week 2
Forums
Week 3–4
Steer & decide
Boardquarterly
Project steering committeemonthly
Project progress meeting, owner + EPCMweekly
Change control boardweekly
Function forums: engineering, planning, cost, supply chainweekly

The first weeks build the facts. The steering forums use them to decide.

Escalation in three steps

1
Function forum

Resolved within function authority, inside 2 working days.

2
Project forum

Owner's team and contractor resolve within project authority.

3
Steering and board

Above threshold or critical: next session, or ad hoc within 48 hours.

Escalations follow the delegation of authority and come with options and a recommendation. Every decision is logged.

Data and dashboards for every level
Board and steering

Portfolio and monthly project report: gate readiness, EAC against funding, critical path, contingency, top risks.

Project forums

Integrated schedule, change log, interface and constraint registers, shared by owner and contractor.

Function forums

Operational KPIs such as document status, productivity factor and look-ahead, each tied to a decision.